October 29, 2026
Patch Reef Park sits a short drive north of Boca Bath and Tennis on Military Trail. For about 18 months it has been rebuilt in stages that were planned so the courts never all shut down at once. The park's tennis, pickleball and practice courts were finished in September 2026. The old community center was set to reopen as the new Community Accessibility Program Center with an Oct. 23 ribbon cutting, and regular hours began Oct. 24.
That means the playground, every court and the main building at 2000 Yamato Road have all been rebuilt or renovated since spring 2025. The park opened in 1983, and most of what a regular visitor uses there has now been redone.
The Greater Boca Raton Beach and Park District owns Patch Reef. The City of Boca Raton runs it. When the District's board approved the court reconstruction on July 7, 2025, the work was phased on purpose. According to the District's September 2026 capital projects report, the plan was for the existing facility never to close all at once, and for the old courts to be rebuilt only after the new covered complex next door was finished.
Here is the order the work happened in:
Each step made room for the next. The covered courts kept pickleball going while the outdoor courts were torn up, and the court work wrapped up just weeks before the community center reopened.
The covered complex was the first of its kind in the city. When the District set the opening date, it called the complex Boca Raton's first covered public pickleball courts. There are 18 courts, two of them ADA-compliant, with lighting, sound, fans, seating, and water and ice. In January 2026 it hosted the first Pickle For Police, the first professional tournament held at the new complex. Proceeds supported local law enforcement through a Corporate/First Responders Cup alongside the pro event.
The less visible project was the one that followed. TAPinto Boca Raton reported in December 2025 that the District had started a two-phase, $2.6 million rebuild of the original courts. Phase one covered 12 pickleball courts and seven tennis courts. In the same article, District executive director Briann Harms explained why the work was overdue:
"Players should notice a significant improvement, as the current courts are well beyond their typical 20-year lifespan and have only been resurfaced over the years rather than fully rebuilt."
According to the District's report, the work included tearing out the old asphalt and fencing, regrading the court base, laying new asphalt and surfacing, and putting in new net posts. The practice areas and the hitting wall were renovated too. Harms told TAPinto the rebuilt courts use the same Laykold Cushion Plus Supreme surface as the covered complex. So for the first time, every court at the club has the same cushioned surface.
As of this fall, the city lists the Patch Reef Park Paddle & Racquet Club with these courts:
| Court type | Count | Status this fall |
|---|---|---|
| Covered pickleball | 18 | Open since October 2025 |
| Outdoor pickleball | 15 | The 12 existing courts were rebuilt, finished September 2026 |
| Outdoor hard tennis | 13 | Rebuilt, finished September 2026 |
You book courts through the club's online booking system, but staff first have to verify your affiliation in person. To establish Palm Beach County resident status, bring a driver's license or photo ID plus a tax statement, notarized lease or utility bill. The club's program page currently lists pickleball open play on weekdays from 7:30 to 11:45 a.m. and from 4:45 p.m. to close, and on weekends from 7:30 a.m. to 1 p.m. It also lists clinics, ladders and tennis classes. Schedules change, so check the page before you drive over.
The community center renovation started out much smaller. In November 2024, the District's board asked staff to work with the city's Recreation Services Department on expanding programs for people with disabilities at the building. The idea built on the success of the District's inclusive playground in the same park.
The first plan was to update the restrooms for ADA compliance. Then, at the Aug. 18, 2025 board meeting, commissioners looked at the age and condition of the building and widened the scope to the whole facility. Architects Walters Zackria Associates designed the expanded plan: a new ADA restroom, new LED lighting and flooring, an accessible kitchen, removal of the old reception area, and a barrier-free multipurpose room. In September 2025, construction was estimated at about $900,000 to $950,000.
The District says these are the first major upgrades to the community center since it opened in the 1980s. During that decade the park also got its tennis center, the first version of the courts that were rebuilt this year.
The CAP Center offers adaptive, sensory-friendly recreation for children and families of all abilities. The District's announcement lists the interactive features: a giant Lite-Brite wall, a Rigamajig building center, magnet walls, a pneumatic air wall, a multiball interactive wall and a sensory pit. Crews also installed a hearing loop under the floors, which amplifies sound for people who need it.
Here are the details from the city, as reported by Boca Post on Oct. 20:
The city is also building a digital library of sensory maps and social scripts. These are meant to help families find their way around community spaces and events outside the park. CAP staff plan to set up tables at events around Boca Raton to explain what accommodations city programs offer. More information is at myboca.us/PatchReefCAP or 561-367-7034.
The rebuilt pieces sit inside a 55-acre park. The city lists baseball and softball fields, basketball, football and soccer fields, a fitness trail with equipment, walking paths, picnic areas, playgrounds, and eight pavilions you can reserve. Fields and courts are first-come, first-served when no permitted activity is using them. The city lights the fields after sunset only for permitted events.
The Pirates Cove playground, first in the sequence, now has wheelchair-compatible swings, accessible slides, a renewed splash pad, shade structures, new picnic and restroom facilities, and ADA parking. With the playground, clubhouse open play and the CAP Center all at Patch Reef, the park now has the setup the District has been building toward since its November 2024 decision to turn the old community center into a center for inclusive recreation.
From the Boca Bath and Tennis gate, the trip is still the same drive north on Military Trail to Yamato Road. What has changed is that the courts and the playground there were rebuilt in 2025 and 2026, and the 1980s community center was renovated into the CAP Center.
Much of daily life around Boca Bath and Tennis happens at places like Patch Reef Park, and The Buchbinder Group follows how this stretch of Military Trail changes. If you're weighing how nearby amenities like these fit into your plans, request a private consultation with our team.
Stay up to date on the latest real estate trends.
Local Knowledge & Lifestyle
Navigating a Yachting Lifestyle.
Boca Raton, FL
Where Luxury Living Meets Exceptional Cuisine
Boca Raton, FL
Travel Ideas For Your Next Trip to Boca Raton, Delray Beach, Palm Beach, Fort Lauderdale, Miami Beach and The Florida Keys
Boca Raton, FL
Your gourmet guide to luxury living.
Exploring Boca Raton’s 2025 housing market forecast.
Boca Raton, FL
The five most sought-after gated communities in Boca Raton.
Local Knowledge & Lifestyle
Your Month-by-Month Guide to Boca Raton & Beyond